Update for the week of October 14, 2026
Construction of the Culligan Water Park Enclosure continued to progress, with ongoing installation of structural steel to advance the building framework. Preparatory work for masonry installation included establishing wall openings and confirming top-of-block elevations. Site servicing also progressed, with pavement cut and excavation completed to accommodate the gas meter and new gas line. Installation of the sump pit also advanced as part of the foundation drainage system.
General view of site looking Southwest showing progress of structural steel installation.
View showing assembled roof trusses in lay down area.
View showing assembled roof trusses in lay down area.
Ongoing installations of pass throughs for underground mechanical.