Project Update - Aug. 26, 2026
Night work has been approved for milling and paving operations on Centennial Drive. Moderate noise is anticipated during these night‑time activities, and we appreciate residents’ patience and understanding while this work is completed.
Milling Operations
Monday, Aug. 31 to Thursday, Sept. 3, 2026 (four nights): Centennial Drive will be fully closed nightly from 7 p.m. to 7 a.m. between Bath Road and Taylor Kidd Boulevard to facilitate surfacing milling operations.
Paving Operations
Monday, Sept. 7 to Thursday, Sept. 10, 2026 (4 nights): Centennial Drive will be fully closed nightly from 7 p.m. to 7 a.m. between Bath Road and Taylor Kidd Boulevard to facilitate surfacing paving operations.
The City thanks residents for their cooperation as we complete these improvements.