Road work will continue on Centennial Drive and Portsmouth Avenue from Oct. 18 to 22, with daytime and overnight construction scheduled.
Overnight paving will take place on Centennial Drive first, followed by Portsmouth Avenue. Residents and motorists may experience construction noise and traffic disruptions. Full road closures will be in place during overnight work, with lane closures expected during daytime construction.
Centennial Drive
- Oct. 18 to 20 (nights): Surface paving, with additional milling at the Taylor-Kidd Boulevard intersection on Oct. 20
- Oct. 19 to 22 (days): Traffic signal upgrades and pavement markings, including work at the Edgar Street intersection
Portsmouth Avenue
- Oct. 19 to 21 (days): Road repairs and preparation for paving
- Oct. 21 and 22 (nights): Surface paving
Work is weather-dependent and schedules may change. For up-to-date information about road and sidewalk closures and other traffic disruptions as a result of road work, visit Municipal511.ca.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends