Project update - July 31, 2026
The general construction schedule is expected to proceed as follows:
- August 4 - 21
- Full road closures from Byron Crescent (south) to Van Order Drive for excavation of the existing road.
- Local and emergency vehicle access will be maintained throughout.
- Full road closures from Byron Crescent (south) to Van Order Drive for excavation of the existing road.
- August 10-18
- Road reconstruction and curb installation from Byron Crescent (south) to Mulcaster Street.
- August 19-31
- Road reconstruction and curb installation from Mulcaster Street to Van Order Drive.
- September 1-14
- Final restoration and surface paving for the full length of Norman RogersDrive.
- School pick-up and drop-off operations will be maintained during construction.
- Final restoration and surface paving for the full length of Norman RogersDrive.
- September 15-24
- Site cleanup
Please note that all dates are subject to change based on weather conditions and construction progress.
For up-to-date information about road and sidewalk closures and other traffic disruptions as a result of road work, visit Municipal511.ca.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends