Project update - July 31, 2026

The general construction schedule is expected to proceed as follows:

  • August 4 - 21
    • Full road closures from Byron Crescent (south) to Van Order Drive for excavation of the existing road.
      • Local and emergency vehicle access will be maintained throughout.
  • August 10-18
    • Road reconstruction and curb installation from Byron Crescent (south) to Mulcaster Street.
  • August 19-31
    • Road reconstruction and curb installation from Mulcaster Street to Van Order Drive.
  • September 1-14
    • Final restoration and surface paving for the full length of Norman RogersDrive.
      • School pick-up and drop-off operations will be maintained during construction.
  • September 15-24
    • Site cleanup

Please note that all dates are subject to change based on weather conditions and construction progress.

For up-to-date information about road and sidewalk closures and other traffic disruptions as a result of road work, visit Municipal511.ca.