This week the contractor will work to complete concrete work for intersections throughout the project. Surface course paving is being scheduled as an overnight operation on Oct. 8, starting at 4 p.m. and ending by 6 a.m. on Oct. 9.
The general construction schedule is expected to proceed as follows:
Oct. 1-7
- Installation of sidewalk ramps and bench pads
- Completing curb installation and base paving at intersections
- Boulevard restoration
Oct. 8
- Surface paving for the full length of Norman Rogers Drive
- Paving is expected to be completed between 4 p.m. on Oct. 8 and 6 a.m. on Oct. 9
- If delayed due to weather, paving will be rescheduled to Oct. 9
- More details will be distributed this week to affected residents
Oct. 9-15
- Installation of pavement markings, speed cushions and raised crossing
- Site restoration and cleanup
Please note that all dates are subject to change based on weather conditions and construction progress.
For up-to-date information about road and sidewalk closures and other traffic disruptions as a result of road work, visit Municipal511.ca.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends