Project update - Oct. 15, 2026

The contractor has completed the majority of the paving for the project. They will complete paving on the side roads and remaining driveways in the next two weeks. This will conclude the bulk of the work; however, delivery of the new streetlighting components has been delayed. The contractor will return in mid-November to finish installing the streetlights and complete final sod restoration.

The general construction schedule is expected to proceed as follows:

Oct. 15-16

  • Surface paving for side roads and driveways
  • Continue installation of concrete sidewalks and bus pads

Oct. 19-23

  • Installation of pavement markings, speed cushions and raised crossing
  • Surface paving for side roads and driveways
  • Complete installation of concrete sidewalks and bus pads
  • Site restoration and cleanup

Mid-late November

  • The contractor will return to install new streetlighting at the new pedestrian crossings
  • Final site restoration and cleanup

Please note that all dates are subject to change based on weather conditions and construction progress.

For up-to-date information about road and sidewalk closures and other traffic disruptions as a result of road work, visit Municipal511.ca.