Project update - Sept. 2, 2026

To assist with the transition into the school year, our contracting partner will be delaying their closure between Van Order Drive and Byron Crescent until further restoration work is completed for the rest of Norman Rogers Drive.

The general construction schedule is expected to proceed as follows:

  • Sept. 2-8 - Start of the school year
    • No full closures on Norman Rogers Drive.
    • The road will be reduced to one lane where crews are working, with personnel on site to direct traffic.
  • Sept. 9-18
    • Curb and sidewalk installation from Mulcaster Street to Van Order Drive.
    • Paving base asphalt from Mulcaster Street to Van Order Drive.
  • Sept. 21-22
    • Surface paving for full length of Norman Rogers Drive and installation of speed cushions and raised crossing.
  • Sept. 23-30
    • Site restoration and cleanup.

Please note that all dates are subject to change based on weather conditions and construction progress.