What We Learned: Gore Road Rest Areas Survey

Why we engaged

The purpose of this engagement is to seek input on where rest areas should be located along the new multi-use pathway on Gore Road. Feedback received will help identify preferred rest area locations and provide valuable input on the overall pathway project. This input will help refine design details while balancing safety, accessibility, and technical requirements.

How we engaged

Images of the project layout, including proposed rest areas, were published on the Get Involved Kingston project page. Users were invited to review the map images and project renderings and submit comments in an online survey from July 7 until July 28. Residents also had the option to submit feedback via phone or email. Feedback submitted via alternate methods was submitted to the survey on Get Involved Kingston.

The opportunity for input was communicated by a news release, direct emails to project followers and Get Involved Kingston users, and social media posts on the City’s channels. The district councillor also helped spread the word in neighbourhood Facebook groups. Additionally, a mailout was sent to nearby neighbours (60m radius from project limits) and posters were put up at nearby locations including the Kingston East Community Centre and the Pittsburgh library branch.

Who we heard from

  • 92 participants completed the survey (16 of them submitted feedback via email and phone)
  • 1,214 visits to project page to learn more
  • 14 new registrations on Get Involved Kingston
  • Locations of respondents (Question 1):
    • 64% live in the neighbourhood immediately adjacent to Gore Road
    • 77% live in Pittsburgh district

What we learned

Feedback on the proposed locations is generally positive, with many comments expressing clear support for the rest stops and broader transportation improvements. A small segment of comments were neutral with no strong opinion but some questions or conditional support. Only a few comments were in opposition to the proposed rest stops and locations.

Overall, there was widespread recognition that rest stops could improve comfort, accessibility and overall user experience for pedestrians and cyclists. Many viewed them as important for seniors, people with mobility challenges, families with strollers and those travelling longer distances.

The following table is a summary of feedback themes identified and responses to each theme.

Rank Feedback Theme MentionsWhat We Heard (Key Specifics & Community Context) Response / Comment

1

Pathway & Cycling Network Support

23

Broad community enthusiasm for separated active transportation, extending bike connections, improved safety over existing narrow shoulders, and closing network gaps to Hwy 15 and Waaban Crossing.

Support for improved active transportation connections is consistent with Council’s strategic priority of fostering an active and connected community.

2

Approval of Proposed Rest Area Concept

13

General agreement that the concept, spacing, and distribution of rest areas along the corridor are logical, well-placed, and much-needed for active transportation users.

Positive feedback on the proposed rest area concept validates planned improvements along the corridor.

3

Rest Stop Micro-Siting Adjustments

10

Specific location modifications requested: shifting stops directly to trailheads (Greenwood Park / Butternut Creek) to accommodate strollers and bikes, setting benches further east away from Hwy 15, adding south-side seating, and utilizing quieter park nodes.

Based on feedback, rest stops were added along the sidewalk on the south side of the corridor, and minor adjustments were made to some proposed rest stop locations.

4

Shade, Tree Canopy & Landscaping

8

North-side seating is exposed to full summer sun; residents strongly requested planting native shade trees near benches, as well as incorporating edible landscaping, pollinator strips, and greenery along the boulevard.

Rest area locations were adjusted to take better advantage of shade from existing trees, with new tree planting proposed where space allows along the corridor.

5

Gore Road Pavement Condition

5

Gore Road is severely deteriorated with potholes, rutting, and hazardous shoulders; strong community expectation that the road will be fully repaved from Dalgleish to Fieldstone alongside path works.

Asphalt and pothole repairs have been completed in the most deteriorated areas to extend the life of the road until planned road work begins in 2027.

6

Hwy 15 / Gore Rd Intersection Operations

5

Safety concerns at Highway 15: requests for bi-directional cycle crossrides (specifically the east crossing) to connect with the north-side multi-use pathway, addressing blind left turns, and improving signal/crosswalk visibility.

Staff will not be altering the Hwy 15 intersection; details are addressed in FAQs.

7

Transit Integration & Bus Stops

4

Ensure rest areas at McLean Park are physically separated from bus stops so Kingston Transit operators do not stop needlessly for trail users; requests for improved shelters at transit stops.

Bus stops are separate from the multi-use pathway rest areas.

8

Commercial Plaza Access & Congestion

3

Rush-hour congestion and turning conflicts at the shopping plaza entrance east of the fire hall; requests for a dedicated right-turn lane and safe mid-block pedestrian crossings between opposite bus stops.

The City has determined a turn lane at the shopping plaza is not warranted based on traffic counts.

9

Amenities & Design Enhancements

3

Inclusion of waste and recycling receptacles at rest pads, interest in public washroom facilities, and suggestions for creative features (permeable pavers, green roofs, public mosaic art).

The installation and placement of waste receptacles along the corridor have been referred to the Public Works department for consideration.

10

Traffic Calming & Alternative Controls

2

Inquiries regarding roundabouts/traffic circles in lieu of traditional stop signs to improve traffic flow, and raised crosswalks/intersections to naturally calm vehicle speeds

Questions about roundabouts and raised crossings have been addressed in the project's FAQs.


Next steps

Results from this survey have been shared with the project team for review, and feedback received above was incorporated into the overall design for corridor improvements. Construction is expected to begin in December 2026. An updated project timeline is listed below:

  • Fall 2026: Detailed Design Phase for corridor improvements is completed

  • December 2026: Construction begins with the Butternut Creek Cross Culvert

  • Winter 2026- 2027: Winter seasonal shutdown

  • Spring 2027: Construction resumes

  • End of 2027: Construction is planned to be completed by the end of 2027