Roadway rehabilitation is planned for Fall 2026 and Spring 2027 on Sutherland Drive.
Project location map
Planned improvements
Full depth asphalt repair on Sutherland Drive from Conacher Drive to Conacher Drive.
Concrete curb repair and structure adjustments.
Intersection improvements
Construction impacts
Construction is expected to begin Fall 2026. Base level asphalt and curb repair is expected to be complete in Fall 2026, followed by a planned winter shutdown. The contractor will return in Spring 2027 to complete surface paving and pavement markings.
Access: Due to the excavation required to reconstruct the road, sections of Sutherland Drive will be closed during construction. Emergency services and local traffic will have access during road closure operations; however, through-traffic will be restricted. The road will remain open overnight and on weekends. The road will remain open during the winter shutdown.
Parking: On-street parking may be reduced or not available during portions of construction.
Stay informed
Updates on project progress, construction impacts, and timelines will be shared on this page. Use the Follow Project feature to receive updates by email.
Roadway rehabilitation is planned for Fall 2026 and Spring 2027 on Sutherland Drive.
Project location map
Planned improvements
Full depth asphalt repair on Sutherland Drive from Conacher Drive to Conacher Drive.
Concrete curb repair and structure adjustments.
Intersection improvements
Construction impacts
Construction is expected to begin Fall 2026. Base level asphalt and curb repair is expected to be complete in Fall 2026, followed by a planned winter shutdown. The contractor will return in Spring 2027 to complete surface paving and pavement markings.
Access: Due to the excavation required to reconstruct the road, sections of Sutherland Drive will be closed during construction. Emergency services and local traffic will have access during road closure operations; however, through-traffic will be restricted. The road will remain open overnight and on weekends. The road will remain open during the winter shutdown.
Parking: On-street parking may be reduced or not available during portions of construction.
Stay informed
Updates on project progress, construction impacts, and timelines will be shared on this page. Use the Follow Project feature to receive updates by email.
Construction on Sutherland Drive is expected to begin as early as Monday, Sept.14, with utility locates being completed in early September. The general construction schedule is expected to proceed as follows:
Sept.14-Oct. 2
Road removal and reconstruction from Virginia Street easterly to Conacher Drive.
Oct. 5-23
Road removal and reconstruction from Virginia Street westerly to Conacher Drive.
Oct. 26-30
Site clean-up and winter shutdown
May 2027
Catch basin adjustments and surface paving
Please note that all dates are subject to change based on weather conditions and construction progress. For up-to-date information about road and sidewalk closures and other traffic disruptions as a result of road work, visit Municipal511.ca.
Construction on Sutherland Drive is expected to begin as early as Monday, Sept.14, with utility locates being completed in early September. The general construction schedule is expected to proceed as follows:
Sept.14-Oct. 2
Road removal and reconstruction from Virginia Street easterly to Conacher Drive.
Oct. 5-23
Road removal and reconstruction from Virginia Street westerly to Conacher Drive.
Oct. 26-30
Site clean-up and winter shutdown
May 2027
Catch basin adjustments and surface paving
Please note that all dates are subject to change based on weather conditions and construction progress. For up-to-date information about road and sidewalk closures and other traffic disruptions as a result of road work, visit Municipal511.ca.
Page last updated: 02 Sep 2026, 02:33 PM
Stay informed
Subscribe for project updates
Summer 2026
Sutherland Drive Roadway Rehabilitation – Transportation Network Improvements is currently at this stage
Detailed design phase
Fall 2026
this is an upcoming stage for Sutherland Drive Roadway Rehabilitation – Transportation Network Improvements
Construction scheduled to start
Spring 2027
this is an upcoming stage for Sutherland Drive Roadway Rehabilitation – Transportation Network Improvements
We use the IAP2 Spectrum of Public Participation to let you know how feedback on a project will be used. Here's how we are seeking and using your feedback on this project.
Inform: We will keep you informed by providing balanced and objective information to assist you in understanding the problem, alternatives, opportunities and/or solutions.
All information received will be compiled and considered by staff for use under the purposes of this site. Information will be collected and used in accordance with the Municipal Freedom of Information and Protection of Privacy Act and other relevant privacy legislation. All comments made on this site are available to the public and may form part of public records.