Sutherland Drive Roadway Rehabilitation – Transportation Network Improvements

Roadway rehabilitation is planned for Fall 2026 and Spring 2027 on Sutherland Drive.

Project location map

Project location map

Planned improvements

  • Full depth asphalt repair on Sutherland Drive from Conacher Drive to Conacher Drive.
  • Concrete curb repair and structure adjustments.
  • Intersection improvements

Construction impacts

Construction is expected to begin Fall 2026. Base level asphalt and curb repair is expected to be complete in Fall 2026, followed by a planned winter shutdown. The contractor will return in Spring 2027 to complete surface paving and pavement markings.

Access: Due to the excavation required to reconstruct the road, sections of Sutherland Drive will be closed during construction. Emergency services and local traffic will have access during road closure operations; however, through-traffic will be restricted. The road will remain open overnight and on weekends. The road will remain open during the winter shutdown.

Parking: On-street parking may be reduced or not available during portions of construction.

Stay informed

Updates on project progress, construction impacts, and timelines will be shared on this page. Use the Follow Project feature to receive updates by email.

Roadway rehabilitation is planned for Fall 2026 and Spring 2027 on Sutherland Drive.

Project location map

Project location map

Planned improvements

  • Full depth asphalt repair on Sutherland Drive from Conacher Drive to Conacher Drive.
  • Concrete curb repair and structure adjustments.
  • Intersection improvements

Construction impacts

Construction is expected to begin Fall 2026. Base level asphalt and curb repair is expected to be complete in Fall 2026, followed by a planned winter shutdown. The contractor will return in Spring 2027 to complete surface paving and pavement markings.

Access: Due to the excavation required to reconstruct the road, sections of Sutherland Drive will be closed during construction. Emergency services and local traffic will have access during road closure operations; however, through-traffic will be restricted. The road will remain open overnight and on weekends. The road will remain open during the winter shutdown.

Parking: On-street parking may be reduced or not available during portions of construction.

Stay informed

Updates on project progress, construction impacts, and timelines will be shared on this page. Use the Follow Project feature to receive updates by email.

  • Project Update - Sept. 2, 2026

    Construction on Sutherland Drive is expected to begin as early as Monday, Sept.14, with utility locates being completed in early September. The general construction schedule is expected to proceed as follows:

    • Sept.14-Oct. 2
      • Road removal and reconstruction from Virginia Street easterly to Conacher Drive.
    • Oct. 5-23
      • Road removal and reconstruction from Virginia Street westerly to Conacher Drive.
    • Oct. 26-30
      • Site clean-up and winter shutdown
    • May 2027
      • Catch basin adjustments and surface paving

    Please note that all dates are subject to change based on weather conditions and construction progress. For up-to-date information about road and sidewalk closures and other traffic disruptions as a result of road work, visit Municipal511.ca.

    Construction on Sutherland Drive is expected to begin as early as Monday, Sept.14, with utility locates being completed in early September. The general construction schedule is expected to proceed as follows:

    • Sept.14-Oct. 2
      • Road removal and reconstruction from Virginia Street easterly to Conacher Drive.
    • Oct. 5-23
      • Road removal and reconstruction from Virginia Street westerly to Conacher Drive.
    • Oct. 26-30
      • Site clean-up and winter shutdown
    • May 2027
      • Catch basin adjustments and surface paving

    Please note that all dates are subject to change based on weather conditions and construction progress. For up-to-date information about road and sidewalk closures and other traffic disruptions as a result of road work, visit Municipal511.ca.

Page last updated: 02 Sep 2026, 02:33 PM